Westfield Barnes Regional Airport

Airport Planning and Engineering Services
Westfield, MA

 

Westfield Barnes Regional Airport

 

Gale’s Services:

  • Planning, design, bidding, permitting, and construction phase services for:
    • Reconstruction of taxiways ‘A’, ‘B’ South, and ‘S’
    • Reconstruction of the intersection of Runway 02-20 and Runway 15-33
    • Runway, taxiway, and apron pavement crack sealing and markings
    • New perimeter fencing, gates, and access control (three phases)
    • Construction of new taxiways ‘B’ North and ‘H’ including airfield signage
    • Airport lighting, rotating beacon, and lighting control upgrades
    • Acquisition of Snow Removal Equipment (SRE) / maintenance equipment
    • Construction of new terminal apron, terminal parking lot, and entrance
  • Rare Species Master Plan
  • Vegetation Management Plan and obstruction removal
  • Part 150 noise exposure study and mitigation plan
  • Runway grooving and runway surface sensor system installation
  • Relocation assistance for federal NAVAIDS
  • Preliminary concept planning, design, and construction phase services for airport terminal building
  • Airport feasibility study to determine airport’s future role
  • Development of $35M 20-year Capital Improvement Plan (CIP)
  • Relocation of arrestor systems, reconstructed runway safety areas
  • Airport Master Plan and Airport Layout Plan Update