George D. Harlow Field: Runway Reconstruction
This $19.3 million project completed in 2014 included permitting, design and construction phase services for the relocation and extension of Runway 06-24 at George D. Harlow Field. Runway 6-24 was shifted, widened, and extended to 3,900’ x 100’. A parallel taxiway, two stub taxiways, and runway safety areas were reconstructed, marked, lit, and signed. Federal and non-federal NAVAIDs were relocated. The project also included construction of wetland replication and turtle habitat areas, a surface and subsurface stormwater drainage system, and temporary and permanent erosion control measures. Vegetative obstructions on and off-airport were removed from approximately 100 acres of wetlands. Extensive coordination efforts by Gale were required to obtain federal, state, and local permits for the project.

During Construction
The Challenges
- Master Plan and ALP require update
- Runway too short and narrow
- Rare species, wetlands, archaeological constraints
- Multiple environmental permits required
- Over 100 acres of tree obstructions in approaches
- Easements required over 11 properties to remove trees
- Up to 40 ft. of peat in proposed runway safety area
- Runway bounded by two rivers
- Residential neighbors surround airport

After Construction
Gale’s Solutions
- Prepared update to Master Plan and ALP
- Prepared Environmental Assessment and State Environmental Review documents
- Lengthened and widened runway and taxiway
- Obtained all easements, and purchased 3 properties
- Planned, designed and coordinated mitigation plans for wetlands, rare species and archaeological resources
- Obtained three federal, three state, and four local permits,
- Constructed new runway/taxiway including:
- Safety areas and airfield lighting/markings/signs
- Wetland replication and restoration areas
- Stormwater/flood detention facilities
- Over 2500 wood piles installed for base of safety areas in peat
- Removed tree obstructions in approaches
- Eliminating peat removal to construct safety areas in wetlands reduced wetland impacts and eliminated substantial truck traffic on residential streets
- Prepared for and represented owner at twelve public hearings